A and B can do a piece of work in 12 days and 39 days, respectively. Both work for 4 days and then A leaves. How long (in days) will B take to complete the remaining work?
- AOption (a)
21
- BOption (b)
22
- COption (c)
24
- DOption (d)
23
View answer & explanationHide answer & explanation
Correct answer
22
Why this answer is correct

Shortcut Trick
Total Work (LCM of 12 and 39) = 156 units.
Efficiencies: A = 13, B = 4.
Work done by (A + B) in 4 days = (13 + 4) × 4 = 68 units.
Remaining work = 156 − 68 = 88 units.
Time taken by B = 88 ÷ 4 = 22 days.
∴ The correct answer is 22 days.

Alternate Method
Given:
Time taken by A = 12 days
Time taken by B = 39 days
Formula Used:
Efficiency = Total Work ÷ Time
Remaining Work = Total Work − Work Completed
| Person | Days | Total Work | Efficiency |
|---|---|---|---|
| A | 12 | 156 (LCM) | 13 |
| B | 39 | 4 |
Calculations:
⇒ Total efficiency of A and B = 13 + 4 = 17 units/day
⇒ Work done by A and B together in 4 days = 17 × 4 = 68 units
⇒ Remaining work to be done = 156 − 68 = 88 units
⇒ A leaves, so B completes the 88 units of work.
⇒ Time taken by B = 88 ÷ 4 = 22 days
∴ The correct answer is 22 days.

Additional Information
Pipes & Cisterns
Similar logic applies to pipes where inlet pipes have positive efficiency and outlet pipes have negative efficiency.
Work & Wages
Wages are distributed among workers in the ratio of their efficiency or the total work done by each.
Alternate Day Work
When people work on alternate days, calculate the work done in one complete cycle (e.g., 2 days) to find the total time.
Efficiency and Time Relationship
Efficiency is inversely proportional to the time taken to complete the work (Efficiency ∝ 1 ÷ Time).