If 20 men can complete a piece of work in 18 days working 5 hours per day, in how many days can 25 men complete it, working 6 hours per day?
- AOption (a)
10 days
- BOption (b)
13 days
- COption (c)
11 days
- DOption (d)
12 days
View answer & explanationHide answer & explanation
Correct answer
10 days