Shortcut Trick
Use the direct inverse relationship formula for constant work:
M1 × D1 = M2 × D2
Substitute the given values into the formula:
⇒ 6 × 10 = 15 × D2
⇒ D2 = 60 ÷ 15 = 4 days
∴ The correct answer is 4 days.
Alternate Method
Given:
Initial number of machines (M1) = 6
Initial number of days (D1) = 10 days
New number of machines (M2) = 15
Formula Used:
Total Work = Number of Machines × Days
| Group | Days | Total Work | Efficiency |
|---|
| 6 machines | 10 | 60 | 6 |
| 15 machines | 4 | 15 | |
Calculations:
⇒ Let the total work be the LCM of work components or the total machine-days required.
⇒ Total Work = 6 machines × 10 days = 60 units
⇒ Let the number of days required by 15 machines be D2.
⇒ 15 × D2 = 60
⇒ D2 = 60 ÷ 15
⇒ D2 = 4 days
∴ The correct answer is 4 days.
Additional Information
Inverse Variation Rule
When work remains constant, efficiency is inversely proportional to the time taken. If the number of machines increases, the days required to complete the same work will decrease proportionately.
General MDH Formula
For complex work structures: (M1 × D1 × H1) ÷ W1 = (M2 × D2 × H2) ÷ W2, where M is resources, D is days, H is working hours, and W is work quantity.
Individual Machine Contribution
If machines operate at the same rate, each individual machine contributes exactly 1/N of the total combined output rate for N machines.