Carpenter A makes 1 chair in 6 hours, Carpenter B makes 1 chair in 7 hours and Carpenter C makes 1 chair in 8 hours. If each Carpenter works 8 hours per day, how many chairs will be made in 21 days?
- AOption (a)
64
- BOption (b)
69
- COption (c)
73
- DOption (d)
78
View answer & explanationHide answer & explanation
Correct answer
73
Why this answer is correct
Given:
Carpenter A makes 1 chair in 6 hours, Carpenter B makes 1 chair in 7 hours and Carpenter C makes 1 chair in 8 hours.
Formula Used:
M × D = total work; M = number of men, D = number of days
Calculation:
⇒ number of chairs made by carpenter A in 8 hr = 8/6 = 4/3
⇒ number of chairs made by carpenter A working 8 hr a day in 21 days = 4/3 × 21 = 28
⇒ number of chairs made by carpenter B in 8 hr = 8/7 unit
⇒ number of chairs made by carpenter B working 8 hr a day in 21 days = 8/7 × 21 = 24
⇒ number of chairs made by carpenter C in 8 hr = 1 unit
⇒ number of chairs made by carpenter C working 8 hr a day in 21 days = 21
⇒ total number of chairs made by them = (28 + 24 + 21) = 73