A, B, C, and D can do a piece of work in 12, 15, 20, and 30 days, respectively. All start together, but D leaves after 2 days, C leaves 3 days before the completion, and B leaves 2 days before the completion. Determine the total time required to complete the work.
- AOption (a)
5 days 20 hours
- BOption (b)
6 days 2 hours
- COption (c)
5 days 10 hours
- DOption (d)
8 days 6 hours
View answer & explanationHide answer & explanation
Correct answer
6 days 2 hours
Why this answer is correct
Shortcut Trick
Total Work = LCM(12, 15, 20, 30) = 60 units. Efficiencies: A=5, B=4, C=3, D=2.
Subtract work of person leaving after starting: 60 − (D × 2) = 60 − 4 = 56 units (D is removed).
Add work of persons leaving before completion: 56 + (C × 3) + (B × 2) = 56 + 9 + 8 = 73 units.
Total time = Adjusted Work ÷ (Sum of efficiencies of A, B, and C) = 73 ÷ 12 = 61/12 days.
Converting fraction to hours: 1/12 × 24 = 2 hours.
∴ The correct answer is 6 days 2 hr.
Alternate Method
Given: Time taken by A = 12 days, B = 15 days, C = 20 days, and D = 30 days.
Formula Used: Total Work = Efficiency × Time | Efficiency = Total Work ÷ Time
| Person | Days | Total Work | Efficiency |
|---|---|---|---|
| A | 12 | 60 (LCM) | 5 |
| B | 15 | 4 | |
| C | 20 | 3 | |
| D | 30 | 2 |
⇒ Let the total time to complete the work be x days.
⇒ D works for 2 days, C works for (x − 3) days, B works for (x − 2) days, and A works for all x days.
⇒ Total work equation: (5 × x) + 4 × (x − 2) + 3 × (x − 3) + (2 × 2) = 60
⇒ 5x + 4x − 8 + 3x − 9 + 4 = 60
⇒ 12x − 13 = 60
⇒ 12x = 73
⇒ x = 73 ÷ 12 = 61/12 days
⇒ 6 days + (1/12 × 24) hours = 6 days 2 hours.
∴ The correct answer is 6 days 2 hr.
Additional Information
Leaving Before vs. After Completion
If a person leaves n days after starting, subtract their work and exclude them. If they leave n days before completion, add their hypothetical work and keep them in the divisor.
Work and Wages
Wages are always distributed in the ratio of the actual work done by each person, which is (Efficiency × Time Spent).
Pipes and Cisterns Analogy
Similar to Time and Work, but inlet pipes have positive efficiency and outlet/leak pipes have negative efficiency.