Shortcut Trick
Total work (LCM of 12, 18, 24) = 72 units.
Efficiencies: Amit = 6, Bharat = 4, Chitra = 3.
Total efficiency = 6 + 4 + 3 = 13 units/hr.
Work done in 4 hr = 13 × 4 = 52 units.
Remaining work = 72 − 52 = 20 units.
Time for Bharat and Chitra = 20 ÷ (4 + 3) = 20 ÷ 7 = 2 6/7 hr.
∴ The correct answer is 2 6/7 hr.
Alternate Method
Given:
Time taken by Amit = 12 hr
Time taken by Bharat = 18 hr
Time taken by Chitra = 24 hr
Time they worked together = 4 hr
Method: LCM Efficiency Table
| Person | Days (hr) | Total Work | Efficiency (units/hr) |
|---|
| Amit | 12 | 72 units | 6 |
| Bharat | 18 | 4 | |
| Chitra | 24 | 3 | |
Calculations:
⇒ Total Efficiency of Amit, Bharat, and Chitra = 6 + 4 + 3 = 13 units/hr
⇒ Work completed in 4 hr = 13 × 4 = 52 units
⇒ Remaining work to be done = 72 − 52 = 20 units
⇒ Combined Efficiency of Bharat and Chitra = 4 + 3 = 7 units/hr
⇒ Time taken by Bharat and Chitra = Remaining Work ÷ Efficiency (B + C)
⇒ Time = 20 ÷ 7 = 2 6/7 hr
∴ The correct answer is 2 6/7 hr.
Additional Information
Time and Efficiency Relationship
The time taken to complete a work is inversely proportional to the efficiency. If a person can do a work in 'n' days, their one day's work is 1/n.
Work and Wages
Wages are distributed among workers based on the ratio of the total work they have individually performed, which often simplifies to the ratio of their efficiencies if they work for the same duration.
Pipes and Cisterns
Concept similar to Time & Work, where an inlet pipe does positive work and an outlet/leakage pipe does negative work.