Question 221

RRB JE 2026• Technical Abilities

In an irrigated plot, the net irrigation requirement of a crop is found to be 14.9 cm, the application efficiency is 80% and the water conveyance efficiency is 70% the gross irrigation requirement is 

  1. AOption (a)

    26.6 cm

  2. BOption (b)

    8.3 cm

  3. COption (c)

    17.0 cm 

  4. DOption (d)

    21.3 cm

View answer & explanation

Correct answer

Answer: (a)A.

26.6 cm

Explanation not yet available.

Question 222

RRB JE 2026• Technical Abilities

Which of the following equations is used to calculate absolute pressure?

  1. AOption (a)

    absolute pressure = gauge pressure- atmospheric pressure 

  2. BOption (b)

    absolute pressure = atmospheric pressure + gauge pressure

  3. COption (c)

    absolute pressure = atmospheric pressure - gauge pressure

  4. DOption (d)

    absolute pressure = gauge pressure- vacuum pressure

View answer & explanation

Correct answer

Answer: (a)A.

absolute pressure = gauge pressure- atmospheric pressure 

Explanation not yet available.

Question 223

RRB JE 2026• Technical Abilities

The cofferdam used when the depth of water is up to 3 m is called

  1. AOption (a)

    Earth fill cofferdam

  2. BOption (b)

    Rockfill cofferdam

  3. COption (c)

    Cellular cofferdam

  4. DOption (d)

    Single wall cofferdam

View answer & explanation

Correct answer

Answer: (a)A.

Earth fill cofferdam

Explanation not yet available.

Question 224

RRB JE 2026• Technical Abilities

The covered area of the proposed building is 150 m2 and it includes a rear courtyard of 5 m × 4 m. If the plinth area rate for similar buildings is Rs.1,250/m2, what is its cost?

  1. AOption (a)

    Rs.1,87,500

  2. BOption (b)

    Rs. 2,12,500

  3. COption (c)

    Rs. 3,75,000

  4. DOption (d)

    Rs. 1,62,500

View answer & explanation

Correct answer

Answer: (a)A.

Rs.1,87,500

Explanation not yet available.

Question 225

RRB JE 2026• Technical Abilities

Pick the odd one out with respect to the type of failure of tension members.

  1. AOption (a)

    Lateral torsional flexural buckling

  2. BOption (b)

    Gross section yielding

  3. COption (c)

    Block shear failure

  4. DOption (d)

    Net section rupture

View answer & explanation

Correct answer

Answer: (a)A.

Lateral torsional flexural buckling

Explanation not yet available.

Question 226

RRB JE 2026• Technical Abilities

According to IS 456:2000, a column is classified as a short column if the slenderness factor about both the major and minor principal axes is less than:

  1. AOption (a)

    22

  2. BOption (b)

    12

  3. COption (c)

    34

  4. DOption (d)

    40

View answer & explanation

Correct answer

Answer: (a)A.

22

Explanation not yet available.

Question 227

RRB JE 2026• Technical Abilities

Why is the dry-mix process preferred over the wet-mix process in shotcreting?

  1. AOption (a)

    It allows admixtures to be used more effectively.

  2. BOption (b)

    It eliminates dust hazards completely.

  3. COption (c)

    It ensures lower creep and greater durability.

  4. DOption (d)

    It allows higher water/cement ratios for better workability.

View answer & explanation

Correct answer

Answer: (a)A.

It allows admixtures to be used more effectively.

Explanation not yet available.

Question 228

RRB JE 2026• Technical Abilities

Cement mortar of fluid consistency used to fill the voids and joints in masonry and to repair the cracks is known as:.

  1. AOption (a)

    guniting and permeability

  2. BOption (b)

    guniting

  3. COption (c)

    permeability

  4. DOption (d)

    grout

View answer & explanation

Correct answer

Answer: (a)A.

guniting and permeability

Explanation not yet available.

Question 229

RRB JE 2026• Technical Abilities

As per IRC recommendations the minimum straight length of approaches on either side of bridge should be _______

  1. AOption (a)

    10 m

  2. BOption (b)

    15 m

  3. COption (c)

    20 m

  4. DOption (d)

    25 m

View answer & explanation

Correct answer

Answer: (a)A.

10 m

Explanation not yet available.

Question 230

RRB JE 2026• Technical Abilities

The process of marking the positions of various foundations and other elements on to the ground as per the drawings is called as -

  1. AOption (a)

    Settlement of foundations

  2. BOption (b)

    Settling of foundations

  3. COption (c)

    Siting of foundations

  4. DOption (d)

    Setting out of foundations

View answer & explanation

Correct answer

Answer: (a)A.

Settlement of foundations

Explanation not yet available.