A man undertakes to do a work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time?
- AOption (a)
75
- BOption (b)
85
- COption (c)
100
- DOption (d)
120
View answer & explanationHide answer & explanation
Correct answer
100
Why this answer is correct
200 men can complete the quarter of work in 50 days
If they continue the work, time taken to complete the remaining work = 3 × 50 = 150 days
[∵ ¾ th of the work is remaining]
But they have to complete in 100 days to finish in time
Time ∝ 1/Number of employees
Let the number of extra employees required to complete the work in time be x
∴ 150/100 = (200 + x)/200
300 = 200 + x
∴ x = 100




