Match List I with List II
| List I | List II | ||
|---|---|---|---|
| (Software Process Model) | (Description) | ||
| A. | Waterfall Model | I. | Software can be developed incrementally |
| B. | Evolutionary Model | II. | Requirement compromises are inevitable |
| C. | Component‐based Software Engineering | III. | Explicit recognition of risk |
| D. | Spiral Development | IV. | Inflexible partitioning of the project into stages |
Choose the correct answer from the options given below :
- AOption (a)
A ‐ IV, B ‐ I, C ‐ III, D ‐ II
- BOption (b)
A ‐ I, B ‐ IV, C ‐ II, D ‐ III
- COption (c)
A ‐ II, B ‐ III, C ‐ I, D ‐ IV
- DOption (d)
A ‐ IV, B ‐ I, C ‐ II, D ‐ III
View answer & explanationHide answer & explanation
Correct answer
A ‐ IV, B ‐ I, C ‐ II, D ‐ III
Why this answer is correct
The correct answer is option 4.
Solution :
| List I | List II | ||
|---|---|---|---|
| (Software Process Model) | (Description) | ||
| A. | Waterfall Model | IV. | Inflexible partitioning of the project into stages |
| B. | Evolutionary Model | I. | Software can be developed incrementally |
| C. | Component‐based Software Engineering | II. | Requirement compromises are inevitable |
| D. | Spiral Development | III. | Explicit recognition of risk |
- The waterfall model is best suited if requirements are easily understandable & defined.
- The spiral model is similar to the incremental development for a system, with more emphasis placed on risk analysis. The spiral model has four phases: Planning, Design, Construct, and Evaluation.