A, B and C together can complete a work in 10 days. A and B together can do the same work in 12 days. If A, B and C received Rs. 9,000 for doing the work together, then what was the share of C from the above amount?
- AOption (a)
Rs. 3,000
- BOption (b)
Rs. 3,750
- COption (c)
Rs. 1,500
- DOption (d)
Rs. 2,250
View answer & explanationHide answer & explanation
Correct answer
Rs. 3,000