Raj is 60% more efficient than Sundar, and Sundar can finish a certain job in 16 days. How many days does Raj alone take to complete the same job?
- AOption (a)
10 days
- BOption (b)
8 days
- COption (c)
days
- DOption (d)
12 days
View answer & explanationHide answer & explanation
Correct answer
10 days
Why this answer is correct
Given:
Raj is 60% more efficient than Sundar.
Sundar can finish a certain job in 16 days.
Formula Used:
Time taken by Raj = Time taken by Sundar / Efficiency Ratio
Calculation:
Efficiency of Sundar = 100%
Efficiency of Raj = 160% = 1.6 × Efficiency of Sundar
Time taken by Raj = Time taken by Sundar / 1.6
⇒ Time taken by Raj = 16 / 1.6
⇒ Time taken by Raj = 10 days
Raj alone takes 10 days to complete the same job.