A and B can complete a work in 12 days and 6 days, respectively. They started doing the work together but after 2 days, B had to leave, and A completed the remaining work alone. The remaining work was completed in ________ days.
- AOption (a)
10
- BOption (b)
9
- COption (c)
8
- DOption (d)
6
View answer & explanationHide answer & explanation
Correct answer
6