Brazen can paint a wall red in 12 days, while Ballary can paint the entire wall in 21 days. If Brazen and Ballari work alternately for one day each from painting the wall to coloring it red, then how many days will it take to paint the entire wall red?
- ((a))
16 days
- ((b))
15 days
- ((c))
14 days
- ((d))
12 days
Show Answer
16 days