A can do a work in 10 days, B can do the same work in 15 days, Then how many days together they will take to complete the same work?
- AOption (a)
5 days
- BOption (b)
6 days
- COption (c)
7 days
- DOption (d)
8 days
View answer & explanationHide answer & explanation
Correct answer
5 days